A consortium consisting of #Alstom, #IJMC & #Pestech will be completing the #aerotrain #replacement #project
Alstom & Pestech were the original contractors, #MAHB terminated the contract in August last year citing Pestech being behind schedule as the reason
Under new agreement, Alstom, the Aerotrain's original equipment manufacturer, will be responsible for coordinating the works to recommence the project and deliver 3 new #trains & 2 lines by 1Q2025
Read more: https://theedgemalaysia.com/node/697672
Alstom and IJM Corp-led JV to complete aerotrain replacement project, confirms The Edge report
Malaysia Airports Holdings Bhd (MAHB) has announced that a consortium consisting of ALSTOM Transport Systems (Malaysia) Sdn Bhd, IJM Construction Sdn Bhd (IJMC) and Pestech Technology Sdn Bhd will be completing the aerotrain replacement project.