@aeva @aud planning poker has to be one of the dumbest things I've experienced. Not so much on the consensus building RE time estimation, but the nonsense "complexity points" thing which ultimately maps to time anyway "1 point is an hour, 4 points is a day, 8 points is a week etc" It's still a time estimation, just with a bogus abstraction wrapped around it for some reason.
Maybe the abstraction exists to make it easier to handwave BS like you dealt with
FWIW the team I work with that used to do points/planning poker ended up ditching it for something roughly similar to how you're doing things.
Usually there's some postmortem done WRT how accurate estimates are vs how long the project ended up taking so we can determine if there's an issue with unanticipated difficulty. Blown estimates tend to fall into the usual suspects. Most recently I red-lit a release due to biz assuming a prerequisite feature existed when it didn't
@aeva @beeoproblem @aud velocity has a different meaning in economics and I wish politicians paid more attention to it
you might recognise "how fast does this same $10 get spent to get different things done?"...