#PMvEng asks Q4: How do you transition from pre-sales to the project implementation team? What steps do you take from pre-sales > project award > actual install? Who’s in your kickoff meetings? Do you have a communication plan or RACI?
#PMvEng asks Q4: How do you transition from pre-sales to the project implementation team? What steps do you take from pre-sales > project award > actual install? Who’s in your kickoff meetings? Do you have a communication plan or RACI?
@jacobyaudio
There are 2 TWO , Kick off meetings or should be.
First the internal Kick off with sales person , SE who was assigned, and PM if possible who will be assigned. You review the SOW IN DETAIL!! You review the Gantt chart and check again reality. You challenge where necessary INTERNALLY.
Second Kick off IS EXTERNAL.This kick off has the same group but it is run by the PM and THE CLIENT IS ON THE PHONE WITH YOUR TEAM. The SOW and time line confirmed with the client.