Ford government plans underwater transmission line through Lake Ontario
Energy Minister Stephen Lecce announced he had approved a recommendation to build the line by the IESO, which will boost supply by 900 megawatts.
#energy #infrastructure #LakeOntario #Canada #Fordgovernment #IESO
https://globalnews.ca/news/11602858/toronto-transmission-line-plan/
Ford government plans underwater transmission line through Lake Ontario
Energy Minister Stephen Lecce announced he had approved a recommendation to build the line by the IESO, which will boost supply by 900 megawatts.
#energy #infrastructure #LakeOntario #Canada #Fordgovernment #IESO
https://globalnews.ca/news/11602858/toronto-transmission-line-plan/
Ford government plans underwater transmission line through Lake Ontario
Energy Minister Stephen Lecce announced he had approved a recommendation to build the line by the IESO, which will boost supply by 900 megawatts.
#energy #infrastructure #LakeOntario #Canada #Fordgovernment #IESO
https://globalnews.ca/news/11602858/toronto-transmission-line-plan/
Ford government plans underwater transmission line through Lake Ontario
Energy Minister Stephen Lecce announced he had approved a recommendation to build the line by the IESO, which will boost supply by 900 megawatts.
#energy #infrastructure #LakeOntario #Canada #Fordgovernment #IESO
https://globalnews.ca/news/11602858/toronto-transmission-line-plan/
Ford government plans underwater transmission line through Lake Ontario
Energy Minister Stephen Lecce announced he had approved a recommendation to build the line by the IESO, which will boost supply by 900 megawatts.
#energy #infrastructure #LakeOntario #Canada #Fordgovernment #IESO
https://globalnews.ca/news/11602858/toronto-transmission-line-plan/
Ford government plans underwater transmission line through Lake Ontario
Energy Minister Stephen Lecce announced he had approved a recommendation to build the line by the IESO, which will boost supply by 900 megawatts.
#energy #infrastructure #LakeOntario #Canada #Fordgovernment #IESO
https://globalnews.ca/news/11602858/toronto-transmission-line-plan/
Ford government plans underwater transmission line through Lake Ontario
Energy Minister Stephen Lecce announced he had approved a recommendation to build the line by the IESO, which will boost supply by 900 megawatts.
#energy #infrastructure #LakeOntario #Canada #Fordgovernment #IESO
https://globalnews.ca/news/11602858/toronto-transmission-line-plan/

Quite an interesting site to see the power demand & generation in Ontario. Also includes a page showing how much power we're importing/exporting at any given moment. Data is being fed directly from IESO.

https://live.gridwatch.ca/home-page.html

#PowerGeneration #Electricity #Hydro #IESO #Ontario #Canada

Gridwatch

See where your power comes from, when the grid is clean and when it's not.

| by Energy Insight
Ontario may need to import electricity during extreme weather: report
The Independent Electricity System Operator says there will be enough supply of electricity generated in Ontario under normal weather conditions.
#globalnews #Canada #IESO #OntarioEnergy #Ontariopolitics
https://globalnews.ca/news/10578838/ontario-energy-outlook-report-import/
Ontario may need to import electricity during extreme weather: report

The Independent Electricity System Operator says there will be enough supply of electricity generated in Ontario under normal weather conditions.

Global News
Ontario may need to import electricity during extreme weather: report
The Independent Electricity System Operator says there will be enough supply of electricity generated in Ontario under normal weather conditions.
#globalnews #Canada #IESO #OntarioEnergy #Ontariopolitics
https://globalnews.ca/news/10578838/ontario-energy-outlook-report-import/
Ontario may need to import electricity during extreme weather: report

The Independent Electricity System Operator says there will be enough supply of electricity generated in Ontario under normal weather conditions.