Maine energy: Much delayed US-Canada hydro project gets go-ahead

By Robin Levinson-King, BBC, April 20, 2023

"#Environmental groups also challenged the permits over concerns about the project's impact on #Maine's #NorthWoods.

"In November 2021, the state held a referendum on whether the project should be cancelled. More than 400,000 people showed up to vote - a huge turnout for a state with a population of 1.3 million.

"Last August, the state's Supreme Court weighed in on the case, ruling that the referendum could not be retroactively applied if CMP had vested rights, kicking it back to a lower court to determine the extent of those rights.

"Thursday's ruling sided with #CMP, who had already spent $450m on construction before the project was halted."

#Hydropower #NaturalResourcesCouncilOfMaine #NRCM #Avangrid #CMP #CleanEnergy #Forests #SaveTheForest #SaveMaineForests

Read more:
https://www.bbc.com/news/world-us-canada-65341572

Maine energy: Much delayed US-Canada hydro project gets go-ahead

A Maine referendum had dealt a blow in 2021 to the $1bn New England Energy Connect project.

BBC News