LRT3 Main Contractor To Pay RM2.73 Million Each Day Of Delay, Says Loke

The Minister of Transport announced that the main contractor needs to pay Rm2.73 million per day for delays in completing the project.

Lowyat.NET
Loke: LRT3 May Begin Operating As Early As April 2026

Transport Minister Anthony Loke revealed that the LRT3 line could begin operating as early as April this year.

Lowyat.NET
Prasarana Explains LRT3 Delay As Testing Hits Technical Hurdles

Rapid KL operator Prasarana Malaysia Berhad has clarified that the Shah Alam Line LRT (LRT3) project remains in the Testing and Commissioning phase, despite growing public expectation that the line…

Lowyat.NET
LRT3 Opening Delayed Again Amid Testing Setbacks

The operational timeline of the Light Rail Transit 3 (LRT3) line has been delayed once again. Previously, it was expected to begin service by the end of the year following the completion of testing…

Lowyat.NET

LRT3 Operations Delayed Again; May Start At Tail-End Of 2025 Or Next Year #anthonyloke #lrt3 #transportation

https://www.lowyat.net/2025/373611/lrt3-operations-delayed-again/

LRT3 Operations Delayed Again; May Start At Tail-End Of 2025 Or Next Year

Transport Minister Anthony Loke has announced that the target date of operations for the Light Rail Transit 3 (LRT3) line has been pushed back to 31 December 2025 or later, depending on the outcome…

Lowyat.NET